Operations research (OR) is a powerful analytical method for problem-solving and decision-making, particularly beneficial in managing organizations. In this field, problems are systematically broken down into simpler parts, solved step-by-step through mathematical analysis, making it easier to understand and implement.

Understanding Operations Research MCQ

Operations Research is the science of rational decision-making. It involves studying, designing, and integrating complex systems, aiming to understand system behaviour and enhance or optimise performance.

Operations Research MCQ

1. ________ are entities whose value is determined from the solution of LPP
– A. objective function
– B. decision variable
– C. constraints
– D. opportunity cost
**Answer:** A. objective function

2. The region of feasible solutions in LPP graphical method is called ____
– A. infeasible region
– B. unbounded region
– C. infinite region
– D. feasible region
**Answer:** D. feasible region

3. The outgoing variable row in the simplex table is called ____
– A. outgoing row
– B. key row
– C. basic row
– D. interchanging row
**Answer:** C. basic row

4. When the solution is degenerate in transportation problem, we add a _
– A. dummy
– B. epsilon
– C. penalty
– D. regret
**Answer:** B. epsilon

5. ______ method is used in Assignment Problem
– A. ncwr
– B. lcm
– C. vam
– D. hungarian
**Answer:** D. hungarian

6. The longest path in the network diagram is called ____
– A. head path
– B. sub path
– C. critical path
– D. sub critical path
**Answer:** C. critical path

7. IF the Minimax are (10, 18, 16) and Maximin are (8, 10, 7). The saddle point is ___
– A. 7
– B. 10
– C. 18
– D. 8
**Answer:** B. 10

8. Pick the wrong relationship:
– A. interfering float = total float – free float
– B. total float = free float + independent float
– C. total float ≥ free float ≥ independent float
– D. free float = total float – head event slack
**Answer:** B. total float = free float + independent float

9. The shortest time in the PERT is called ______ time
– A. expected
– B. pessimistic
– C. optimistic
– D. most likely
**Answer:** C. optimistic

10. The total time required to complete all the jobs in a job sequence problem is known as ______
– A. processing order
– B. idle time
– C. processing time
– D. elapsed time
**Answer:** D. elapsed time

11. Operations Research Models in which values of all variables and all possible outcomes are known with certainty are called models.
– A. physical
– B. symbolic
– C. deterministic
– D. probabilistic
**Answer:** C. deterministic

12. Operations Research Models in which some or all variables are random in nature are called models.
– A. physical
– B. symbolic
– C. deterministic
– D. probabilistic
**Answer:** D. probabilistic

13. ______ are techniques applied in project management.
– A. cpm and pert
– B. assignment & transportation
– C. game theory
– D. decision theory & inventory models
**Answer:** A. cpm and pert

14. ______ are the entities whose values are to be determined from the solution of the LPP.
– A. objective function
– B. decision variables
– C. constraints
– D. opportunity cost
**Answer:** B. decision variables

15. ______ specifies the objective or goal of solving the LPP.
– A. objective function
– B. decision variables
– C. constraints
– D. opportunity cost
**Answer:** A. objective function