BSPHCL New Electricity Connection Form (Low Tension Supply) - Summary
Bihar State Power Holding Company Limited (BSPHCL) offers a straightforward process for obtaining a new electricity connection through the BSPHCL New Electricity Connection Form (Low Tension Supply). Here, you can easily download the form in PDF format using the link provided below.
BSPHCL New Electricity Connection Form (Low Tension Supply)
To help you navigate the submission procedure for the BSPHCL New Electricity Connection Form, check the steps outlined below:
- The applicant should obtain the form from the respective office (ensure to pay for the form if required) or can simply download the form using the link below.
- After filling out the application, submit it along with the required documents to the concerned authorities at the respective office. (Make sure to include the licensed electrical contractor who will handle the wiring.)
- The authorities will verify the submitted documents. If everything is in order, they will inform the applicant to pay the necessary fee for this procedure.
- Once the payment is made, a receipt will be issued. Keep it safe for future reference.
- This application will undergo internal processing, and a technician will visit the premises on a planned date, accompanied by the applicant.
- At the end of the survey, the technician will determine where to install the meter and the entry point for supply mains and other necessary equipment. He will also prepare a survey report.
- If the report indicates that supplying electricity is feasible, the applicant will receive notification about the sanction.
- If the applicant fails to comply within the specified period according to the norms from the date of power sanction, both the power sanction and registration will be canceled.
- If the report shows that it is not feasible, the applicant will need to bear the extra costs for making the required conditions viable as advised by the department.
- Next, visit the office to inquire about the service line charges, initial security deposit, and costs for the meter/metering equipment, etc. Make the necessary payment and get a receipt along with your application number.
- Once all the above-mentioned procedures are completed, the electricity department/company will issue the work order.
- Following this, the concerned Junior Engineer/Assistant Engineer will arrange to provide the power supply.
- A pole will be installed, and the applicant must submit the test report with the help of a licensed electrical contractor prior to receiving the electrical connection.
Download the BSPHCL New Electricity Connection Form (Low Tension Supply) PDF using the link provided below.