Here is the step-by-step submission procedure for the BSPHCL New Electricity Connection Form (High Tension Supply).

  1. The applicant should visit the respective office to obtain the form (if needed, please pay for it) or download the form from the link below.
  2. After filling out the application, submit it along with all required documents to the relevant authorities at the office. Remember to include the licensed electrical contractor who will do the wiring.
  3. The authorities will check the submitted documents. If everything is in order, they will instruct the applicant to pay the required fee.
  4. Once you make the payment, a receipt will be issued. Keep this receipt safe for future reference.
  5. This application will go through internal processing, and a technician will schedule a visit to inspect the premises in the presence of the applicant.
  6. At the end of the inspection, the technician will mark where the meter will be fixed, as well as the entry point for supply mains and other equipment. He will also complete the survey report.
  7. If the survey report confirms that supplying electricity is feasible, the applicant will receive a notification about the sanction.
    1. If the applicant does not comply within the specified period from the date of power sanction, both the power sanction and registration will be canceled.
    2. If the report indicates that it is not feasible, the applicant may need to bear the extra costs to meet the required conditions as advised by the department.
  8. Next, visit the office to find out the charges for the service line, initial security deposit, meter costs, etc. Make the necessary payment and obtain the receipt along with your application number.
  9. Once all the aforementioned procedures are completed, the electricity department/company will issue the work order.
  10. Then, the concerned Junior Engineer or Assistant Engineer will arrange to provide the power supply.
  11. A pole will be installed, and the applicant must submit the test report with the help of a licensed electrical contractor before the electrical connection can be provided.